The plumbing and heating pack
- Sections: Preparation and access, Supply, Installation, Testing and commissioning, Making good, Removal and disposal.
- Items it recognises: sink or basin, tap, radiator, boiler, cylinder, pipework, leak, valve, shower, toilet.
- Standard exclusions: hidden pipework found in poor condition once opened up; decorating beyond making good; electrical work beyond the appliance connection.
A combi swap, the Quote Metric way
You arrive, tap Start Site Visit, and talk as you look. "Kitchen. Existing Worcester combi, about twelve years old. Customer wants it on the same wall. Flue goes straight out the back, looks fine. No filter on it. Condensate runs to the sink waste." You photograph the boiler, the flue terminal, the gas meter and the pipework under the boiler. Upstairs: "Bathroom. Radiator under the window, wants a towel rail instead, same centres."
By the time you are back in the van, the visit is typed up. Quote Metric has found a boiler replacement in the kitchen and a towel rail in the bathroom, each with the words and photos behind it, and no prices. You accept them, and they are priced from your price book.
Then it asks what a careful estimator would ask.
The questions it asks
For a boiler:
- Flue kit and any extension allowed for?
- Magnetic filter allowed for?
- Power flush or chemical clean of the system?
- Controls or thermostat allowed for?
- Condensate route allowed for?
- Gas supply checked and allowed for, by a Gas Safe registered engineer?
- Building Regulations notification and benchmark allowed for?
For a radiator or towel rail: new valves, draining down and refilling, inhibitor, brackets and fixings, and pipework alterations to new centres.
For a sink or basin: the tap, the waste and trap, flexible connectors and isolation valves, removal, disposal, leak testing, and making good around the worktop and splashback.
Each question is answered by a line on the estimate, a stated exclusion, or a tick that it is not needed. The quote waits until they are. That is the difference between a £40 waste kit you pay for yourself and one the customer pays for.
Prices that are yours
Your labour rate and your common parts sit in Materials and rates. For the boiler itself, upload the merchant's quote: Quote Metric reads the lines and you choose which to use, with the merchant, document and date kept against the price. When the merchant's quote runs out, Quote Metric stops a fixed quote going out on the old price until you refresh it.
A Quote Template for your standard combi swap saves the sections and lines you always include, so a new job starts from your usual scope, then the visit adds what is different about this one.
VAT on heating work
If you are VAT registered, most work is at 20 percent, but some is not. The installation of qualifying energy saving materials in homes, including heat pumps, is zero rated in Great Britain until 31 March 2027, then reverts to the 5 percent reduced rate. A gas boiler is not an energy saving material for this relief. Set the VAT per quote with your accountant's advice. Read VAT on trade quotes.
What Quote Metric does not do
It does not issue Gas Safe certificates, benchmark checklists or Building Regulations notifications. Keep the system you use for those. Quote Metric gets you to an accepted, signed quote and keeps the agreement, variations and payments with it.
Common questions
Can I quote a heat pump in Quote Metric?
Yes. Use your own price book and a template for your usual installation. The plumbing and heating pack's questions cover the boiler, radiator and sink items it recognises; for a heat pump, your template is where your standard inclusions live.
Can the customer choose between two boilers?
Yes. Put the second boiler in as an option. The customer picks on the link, and the total they accept is worked out again on the server from the version you issued.
What about a callout with an unknown fault?
Send a budget estimate with the allowance stated as an allowance, then firm it up into a quote once you have opened it up.