In short
- Work through the job in order: strip out, first fix, boarding and preparation, tiling, second fix, decoration and making good, removal and disposal.
- List every fixture, and say who supplies each one.
- Price or exclude the unknowns: the subfloor, the walls behind the tiles, the electrics.
- Write down the assumptions: the room is empty, and choices are made before the start date.
Stage by stage
Strip out
- Remove the existing suite, tiles, boxing and flooring.
- Isolate and cap services.
- Protection of floors and stairs on the way in and out.
First fix
- Pipework alterations for the new layout: basin, toilet, bath or tray, shower valve.
- Waste runs and falls, especially for a shower tray or wet room.
- Electrical first fix by a registered electrician: extractor, lighting, shaver point, any underfloor heating.
Boarding and preparation
- Tile backer board or plasterboard where needed.
- Floor preparation: overboarding, levelling, or replacing damaged sections.
- Tanking or waterproofing in the wet areas. Say where and with what.
Tiling
- Wall and floor areas in square metres, with an allowance for waste and cuts.
- The tile itself: supplied by you at a stated price per square metre, or by the customer.
- Adhesive, grout, trims and sealant. Easy to forget, never cheap.
Second fix
- Every fixture listed by name: basin and tap, toilet, bath or tray, screen or curtain rail, shower valve and head, towel rail or radiator, mirror, accessories.
- Connecting, sealing and testing.
- Electrical second fix and certification by the electrician.
Decoration and making good
- Ceiling and walls not tiled: filled, painted, and to what standard?
- Door, architrave and skirting: replaced, adjusted or untouched?
Removal and disposal
- Skip or trips to the tip, and any permit for a skip on the road.
The questions that settle disputes
- Who supplies what? If the customer buys the suite, say so, and say that its condition and fit are their responsibility.
- What finish are they expecting? "Tiled floor to ceiling" or "half height"? Matt or gloss?
- What happens if the floor is rotten? Price an allowance or exclude it, but say which.
- Are choices made? Tiles and fittings chosen before the start date, or the date moves.
- How long without a bathroom? Say how many days, and whether a toilet is kept working overnight.
Electrics and ventilation
Electrical work in a room with a bath or shower is often notifiable under Building Regulations in England, so use a registered electrician who can self certify, and include their price or state that it is by others. Check the extract ventilation requirement in Approved Document F for the room, and include the fan and its ducting.
Send a proposal for the big ones
A full bathroom is a big, personal purchase. A proposal with photos of what you found, how you will do it and the options side by side, such as a standard tray or walk in, chrome or matt black, does more selling than a list of lines. Keep the same figures as the quote. Read quote, proposal or budget estimate.
How Quote Metric helps
Quote Metric's bathroom pack lays the estimate out in these stages and asks ten questions before a bathroom quote can go: access and protection, strip out, waste removal, finishes, adhesive and trims, every fixture, customer supplied items, electrics, tanking, and making good. Its standard exclusions cover the subfloor and customer supplied items. See the bathroom pack.
Common questions
Should I price tiles per square metre?
For the tile itself, a price per square metre with a stated allowance for waste is clear and fair. Put the fixing materials and labour in their own lines.
How do I handle a customer who changes their mind on tiles?
Record the change as a variation with its price before you order. Different tiles can mean different adhesive, trims and labour.